Farrans has announced that it has successfully installed the first turbine at Yellow River Wind Farm in Rhode, County Offaly.
The 101MW wind farm is on track to be commissioned in early 2025. Farrans has been appointed by SSE Renewables as the main construction for the project. Up to 80 full time construction jobs are expected to be created during peak delivery of the project.
Wind turbine supplier Nordex Group has been commissioned by SSE Renewables to manufacture, deliver and install a total of 29 of its N117/3600 turbines at the 101MW Yellow River project site, the first of which was installed last week.
The first convoys of turbine components, delivered to the Midlands site from the Port of Galway, got underway in November 2023 with the installation programme beginning shortly after.
Deliveries are expected to continue until April 2024 and are taking place between midnight and 4am to ensure minimum disruption to local residents.
Yellow River has secured a contract for all of the site's planned installed capacity of renewable energy power under the Irish Government’s latest RESS 3 auction round for new onshore wind farms. The contract is due to commence shortly after commissioning.
When complete, the wind farm will generate enough low-carbon renewable energy to power 66,000 homes annually and offset 65,000 metric tonnes of carbon per annum, which will contribute significantly to Ireland’s 2030 renewable energy targets.
Heather Donald, SSE Renewables' Onshore Renewables Development and Construction Director said: "Celebrating another milestone at Yellow River so soon after taking delivery of the first turbine components underlines the hard work by everyone involved in the installation programme. It is a pivotal moment in the project as our teams continue to press on with a busy schedule to safely install and deliver turbines at the site.
"Achieving this milestone is symbolic of our continued commitment to delivering greener, homegrown energy for Ireland which is needed now and in the future. Across SSE Renewables, we are spending around €4.5m a day on developing and building new clean power assets such as Yellow River Wind Farm. When completed next year, Yellow River will be able to generate in excess of 100MW of wind-powered electricity, contributing significantly to Ireland’s 2030 renewable energy targets."
James Lappin, Project Manager for Nordex said: "The installation of the first turbine at Yellow River Wind Farm is a significant milestone in our commitment to providing innovative wind energy solutions that contribute to a greener, more sustainable future in Ireland. We are proud to partner with SSE Renewables on this 101 MW project and thank the local community for their continued support and patience during the delivery and installation phase. Our teams are working diligently to deliver a safe and timely project whilst also minimising any potential disruption. We look forward to a smooth conclusion to this stage of the project later this year."
Time and date
CONSTRUCTION DIRECTORY
Latest Construction News
29/11/2024
Plans for a new housing development in Carney, Co. Sligo, have significantly progressed after a contract for construction was signed by County Council members. The development, which was designed by Hamilton Young Architects and will be constructed by Kilcawley Construction, consists of 25 homes ...
29/11/2024
South Dublin-based Killinarden Park has officially opened following improvement works. Nicholas de Jong Associates carried out the planning and design work on the project with Clonmel Enterprises Ltd civil contractors realising the vision on the ground. Enhancements to the park include provision ...
29/11/2024
Water supply has been restored to the vast majority of impacted areas in Galway City following repairs, Uisce Éireann has announced. Detection crews from the company isolated the source of a significant burst which occurred in the Docks area of the city yesterday, with works being carried out this ...
29/11/2024
A refurbished running track and new padel courts were officially opened in Greystones, Co. Wicklow, this week. An Taoiseach Simon Harris officially opened the track and padel courts, based at Shoreline Leisure, while also present were the Cathaoirleach of Wicklow County Council, Cllr Paul O Brien, ...
29/11/2024
The Construction Employers Federation (CEF) and Northern Ireland Federation of Housing Associations (NIFHA) have raised major concerns regarding the approved proposal to increase the Standard Connection Charge for a newbuild house by 123% in 2025. The proposal, put forward by NIE Networks to the ...
29/11/2024
Green infrastructure improvements have been successfully completed at Claudy Country Park in L'Derry. Upgrades to the play area at the location as well as safety and access works in the wider park were carried out as part of the green infrastructure enhancement project, which was made possible by ...
28/11/2024
Plans to build 674 new homes in the Clooney Road area of L'Derry have been given the green light. South Bank Square submitted the application, which entails a residential development comprising 33 detached and 473 semi-detached dwellings as well as 168 apartments, to Derry City and Strabane ...
28/11/2024
A new wastewater treatment facility in Ballyronan, Co, L'Derry, has been successfully completed following an investment of £5m from NI Water. GEDA Construction was the main contractor for the 18-month contract, while Water Solutions Ireland completed extensive mechanical and electrical ...
28/11/2024
The Clontarf to City Centre (C2CC) Active Travel Project has officially been opened by Dublin City Council. The project connects the Royal Canal Greenway to the East Coast Trail and part of the Tolka Valley Greenway, providing a safe, pleasant and continuous segregated walking and cycling route ...
28/11/2024
Approximately €1.5 million in payments have been processed under the Vacant Property Refurbishment Grant scheme in Offaly. The grant, which aims at turning vacant or derelict houses and buildings into permanent homes or rental properties, has thus far saw 129, out of 196, applications approved in ...