A seventh and final turbine has been installed during the construction of Lenalea Wind Farm in County Donegal.
The milestone follows close collaboration with EirGrid who has completed commissioning and energisation of Lenalea's 110kV loop in substation, resulting in the site now being connected to the national transmission system. The connection to the grid paves the way to the commencement of the commissioning of the turbines. The commissioning and testing of the turbines will take place from August to October 2023, following which it is anticipated to have the site will be fully operational in November 2023
The 30.1MW onshore wind project is a joint venture between SSE Renewables and FuturEnergy Ireland and is located around 10km southwest of Letterkenny. Once operational, the site could power up to 20,000 Irish homes each year and offset 24,500 tonnes of carbon per annum, contributing to the delivery of Ireland’s 2030 renewable energy targets.
SSE Renewables, the lead developer on the project, will also be responsible for the management of the project in the operations phase, which is scheduled to commence in late 2023. A Community Fund will be available once the project becomes operational. Delivery of the Lenalea Wind Farm project represents a joint total capital investment of over €40 million by development partners SSE Renewables and FuturEnergy Ireland.
Time and date
CONSTRUCTION DIRECTORY
Latest Construction News
15/11/2024
An emergency road closure has been announced following serious structural integrity concerns of the former Antrim Arms Hotel building on Castle Street in Ballycastle. Following genuine fears surrounding the safety of the building's structure, Causeway Coast and Glens Borough Council have ...
15/11/2024
A pre-design public consultation for the Dublin-based College Green - Dame Street Public Realm Project has been launched. The proposal to remodel College Green and Dame Street is a joint initiative by Dublin City Council and the National Transport Authority. The project aims to transform Dublin's ...
15/11/2024
A new plan which aims to fill vacant homes and revitalise derelict buildings has been proposed by Ireland's Green Party. The Dereliction and Building Regeneration Bill put forward by the party aims to establish a single permitting system for fire, accessibility and planning in a one-stop-shop for ...
15/11/2024
Works will begin next week to provide a more reliable water supply in County Kildare, Uisce Éireann has announced. The improvements, which will take place in Allenwood, will also target the reduction of high levels of leakage. GMC Utilities Group are carrying out the works on behalf of Uisce ...
15/11/2024
Essential wastewater improvements being made to the North Street area in Carrickfergus are set to be completed on Friday, November 22, NI Water has announced. Further works will recommence to the area on January 6, after the busy Christmas period. The work is part of a major investment to improve ...
15/11/2024
A forthcoming road closure in Wicklow has been announced by the County Council ahead of essential roadworks which are suspected to last a week. The closure will impact the L-69052 road in Arklow and will take place on the junction of the L2901, Laffin's Lane and The Brook, from Monday, November ...
14/11/2024
A L'Derry park was visited by the Minister of Agriculture, Environment and Rural Affairs yesterday following the completion of extensive works. Manor Park in Moneymore welcomed Minister Andrew Muir MLA, who made the trip to see the result of extensive works which totalled £260,000. The ...
14/11/2024
A Railway Order planning application will be made by Transport Infrastructure Ireland (TII) regarding the major Luas Finglas project. The application will be submitted to An Bord Pleanála on Monday, November 18, while the public can make submissions about the proposed light rail line from November ...
14/11/2024
A new €8.8 million social housing scheme officially launched in County Louth recently. The Ferrard Park development in Drogheda contains 28 new houses which were acquired by Louth County Council from CFS Homes for tenants from the council's social housing waiting list. The houses, which include a ...
14/11/2024
A number of projects across Wicklow aimed at addressing the negative impacts of climate change have received a significant cash boost. Wicklow County Council and The Department of the Environment, Climate and Communications announced an allocation of €675,574.33 to 20 community groups across the ...