A major construction milestone has been marked on the Translink Culvert Strengthening Programme with the completion of the first phase.
FP McCann managed and delivered Phase 1, which is part of an ongoing project to rehabilitate the entire rail network's culvert structures.
The rail network's culverts are basic but essential components of that infrastructure. They carry waterways under the live rail infrastructure and prevent damage from flooding and erosion. The works involved the open cut replacement of 3no. culverts on the Bleach Green to Larne Line and 1no. on the Coleraine to Ballymoney Line as well as the relining of a further 6no. culverts with UV cured in place glass reinforced plastic (GRP) liners on the Belfast to Portadown Line, Ballymoney to Coleraine Line and the Bleach Green to Larne Line.
The open cut replacement works involved the entire replacement of 4no. culverts with precast concrete spigot and socket pipes and bespoke designed segmental precast concrete headwalls manufactured and supplied by FP McCann's Precast Factory in Knockloughrim. Rock armour and scour protection was supplied from a combination of FP McCann's quarries, namely Loughside Quarry in Larne and Bradley's Quarry in Kilrea and installed at both the inlet and outlet of each of the four culverts replaced in accordance with the specification and construction drawing.
Two of the culverts were replaced in conjunction within a single 56-hour Line Blockade with the remaining two installed in subsequent 56-hour blockades in concurrently with other planned significant and strategic rail infrastructure works.
The remaining six culverts within this contract were relined with UV cured-in-place pipe (CIPP) liners to ensure their serviceability for a further 120 years. The resin-soaked liners (prior to curing) are sensitive to temperature and must be kept refrigerated until installation. This and the significant logistical challenges in accessing the culvert locations while ensuring the unimpeded operation of the rail network were challenges overcome in the delivery of this project. This was achieved through a combination of night and day shifts utilising several varying safe systems of works, plant and equipment. In conjunction with the relining, existing brick headwalls and brick scour protection aprons on the Belfast to Portadown culverts were repaired and repointed. New precast concrete headwalls supplied by FP McCann's Precast facility in Knockloughrim and scour protection from FP McCann's Bradley's Quarry in Kilrea were installed at the Ballymoney to Coleraine line culvert in accordance with the specification and construction drawings.
Time and date
CONSTRUCTION DIRECTORY
Construction News
23/06/2022
Translink Culvert Strengthening Programme Reaches Key Milestone
Latest Construction News
15/11/2024
An emergency road closure has been announced following serious structural integrity concerns of the former Antrim Arms Hotel building on Castle Street in Ballycastle. Following genuine fears surrounding the safety of the building's structure, Causeway Coast and Glens Borough Council have ...
15/11/2024
A pre-design public consultation for the Dublin-based College Green - Dame Street Public Realm Project has been launched. The proposal to remodel College Green and Dame Street is a joint initiative by Dublin City Council and the National Transport Authority. The project aims to transform Dublin's ...
15/11/2024
A new plan which aims to fill vacant homes and revitalise derelict buildings has been proposed by Ireland's Green Party. The Dereliction and Building Regeneration Bill put forward by the party aims to establish a single permitting system for fire, accessibility and planning in a one-stop-shop for ...
15/11/2024
Works will begin next week to provide a more reliable water supply in County Kildare, Uisce Éireann has announced. The improvements, which will take place in Allenwood, will also target the reduction of high levels of leakage. GMC Utilities Group are carrying out the works on behalf of Uisce ...
15/11/2024
Essential wastewater improvements being made to the North Street area in Carrickfergus are set to be completed on Friday, November 22, NI Water has announced. Further works will recommence to the area on January 6, after the busy Christmas period. The work is part of a major investment to improve ...
15/11/2024
A forthcoming road closure in Wicklow has been announced by the County Council ahead of essential roadworks which are suspected to last a week. The closure will impact the L-69052 road in Arklow and will take place on the junction of the L2901, Laffin's Lane and The Brook, from Monday, November ...
14/11/2024
A L'Derry park was visited by the Minister of Agriculture, Environment and Rural Affairs yesterday following the completion of extensive works. Manor Park in Moneymore welcomed Minister Andrew Muir MLA, who made the trip to see the result of extensive works which totalled £260,000. The ...
14/11/2024
A Railway Order planning application will be made by Transport Infrastructure Ireland (TII) regarding the major Luas Finglas project. The application will be submitted to An Bord Pleanála on Monday, November 18, while the public can make submissions about the proposed light rail line from November ...
14/11/2024
A new €8.8 million social housing scheme officially launched in County Louth recently. The Ferrard Park development in Drogheda contains 28 new houses which were acquired by Louth County Council from CFS Homes for tenants from the council's social housing waiting list. The houses, which include a ...
14/11/2024
A number of projects across Wicklow aimed at addressing the negative impacts of climate change have received a significant cash boost. Wicklow County Council and The Department of the Environment, Climate and Communications announced an allocation of €675,574.33 to 20 community groups across the ...