Construction Ireland Construction Directory
Time and date
CONSTRUCTION DIRECTORY
Share this page
Construction News
26/05/2021

GRAHAM Completes Part Of Railway Bridge Works Programme

Construction News Image
Construction firm GRAHAM has completed part of a railway bridge replacement and refurbishment works programme, incorporating a 72-hour single event possession, on the Ballymena to Coleraine rail line.

Three major sites, namely the Braid Bridge, Coolderry Bridge and the Culbreen Bridge, were all part of the Translink commissioned contract that was awarded in late January 2021.

Before construction work could commence, an intensive two month planning process was required, which resulted in the identification of a more efficient 72-hour single possession solution as opposed to an original two-pronged possession plan totalling 108 hours.

This innovative approach considerably reduced disruption to the rail network by a full day and a half (36 hours) and also allowed the GRAHAM team to de-risk the programme for two of the bridges.

As part of the package of works, the existing Culbreen Bridge structure was demolished, meaning costly ongoing maintenance is no longer required.

-- Advertisement --

The underside of the entire deck and outer edges of the Coolderry Bridge underwent hydro-demolition before the existing steelwork was drilled for reinforcement to be laid and the surface shot-creted. These important bridge strengthening works, conducted for the first time during a disruptive rail possession, have restored the bridge’s weight restriction to its original design of 40 tonnes.

The Braid Bridge works, on a four-arch masonry structure over the River Braid in Ballymena, involved the removal of 70m of twin track, sleepers, ballast and structural fill. Subsequently, the bridge was waterproofed and reinstated, extending the life span of the structure. The track was also re-laid, welded and stressed.

The works were completed ahead of programme, allowing early handback of the network.

Andrew Henry, GRAHAM Contracts Manager, said: "Generally, a multi-site scheme of this complexity would require a prolonged period of advanced planning and programming, sometimes as much as nine months. Demonstrating our technical competency, we were able to develop a more effective solution of a 72-hour single event possession in as little as two months. This ensured a more efficient process and reduced disruption to the network. Significantly, our waterproofing work, involving loose laid sheeting, was the first of its type to be carried out on a 'live' Translink asset for a considerable length of time.

"Overall, our planning and delivery reflect the successful long-term collaborative relationship that we have developed with Translink, and we look forward to working in partnership on further schemes to future-proof the local rail network."

Latest Construction News

15/11/2024

An emergency road closure has been announced following serious structural integrity concerns of the former Antrim Arms Hotel building on Castle Street in Ballycastle. Following genuine fears surrounding the safety of the building's structure, Causeway Coast and Glens Borough Council have ...
15/11/2024

A pre-design public consultation for the Dublin-based College Green - Dame Street Public Realm Project has been launched. The proposal to remodel College Green and Dame Street is a joint initiative by Dublin City Council and the National Transport Authority. The project aims to transform Dublin's ...
15/11/2024

A new plan which aims to fill vacant homes and revitalise derelict buildings has been proposed by Ireland's Green Party. The Dereliction and Building Regeneration Bill put forward by the party aims to establish a single permitting system for fire, accessibility and planning in a one-stop-shop for ...
15/11/2024

Works will begin next week to provide a more reliable water supply in County Kildare, Uisce Éireann has announced. The improvements, which will take place in Allenwood, will also target the reduction of high levels of leakage. GMC Utilities Group are carrying out the works on behalf of Uisce ...
15/11/2024

Essential wastewater improvements being made to the North Street area in Carrickfergus are set to be completed on Friday, November 22, NI Water has announced. Further works will recommence to the area on January 6, after the busy Christmas period. The work is part of a major investment to improve ...
15/11/2024

A forthcoming road closure in Wicklow has been announced by the County Council ahead of essential roadworks which are suspected to last a week. The closure will impact the L-69052 road in Arklow and will take place on the junction of the L2901, Laffin's Lane and The Brook, from Monday, November ...
14/11/2024

A L'Derry park was visited by the Minister of Agriculture, Environment and Rural Affairs yesterday following the completion of extensive works. Manor Park in Moneymore welcomed Minister Andrew Muir MLA, who made the trip to see the result of extensive works which totalled £260,000. The ...
14/11/2024

A Railway Order planning application will be made by Transport Infrastructure Ireland (TII) regarding the major Luas Finglas project. The application will be submitted to An Bord Pleanála on Monday, November 18, while the public can make submissions about the proposed light rail line from November ...
14/11/2024

A new €8.8 million social housing scheme officially launched in County Louth recently. The Ferrard Park development in Drogheda contains 28 new houses which were acquired by Louth County Council from CFS Homes for tenants from the council's social housing waiting list. The houses, which include a ...
14/11/2024

A number of projects across Wicklow aimed at addressing the negative impacts of climate change have received a significant cash boost. Wicklow County Council and The Department of the Environment, Climate and Communications announced an allocation of €675,574.33 to 20 community groups across the ...
Daniel Keane Architectural TechnologistsR & M Buckets LtdShanette ShedsOliver Crampton & Sons LtdOMP OMeara Plant PartsSwords Auto [Traffic Management]SLG Traffic ManagementO&O ConservatoriesP McVey Building SystemsHS Renewables
Terms and Conditions
2024/11/16 05:26:11