Northern Ireland Roads Minister Conor Murphy has detailed the progress on a £5.5m maintenance and local transport scheme in the Dungannon area.
Work on the A4 Dungannon to Ballygawley dual carriageway and single carriageway realignments on the Ballygawley to Aughnacloy and Ballygawley to Augher roads began earlier this year.
Mr Murphy said construction has largely focused on the Ballygawley end of the project with the excavation and reuse of one million tonnes of material.
"A number of structures which carry the new road over the minor roads are nearing completion namely Armalaughey Road, Goland Road and Farriter Road," said the Minister.
He said: "Others on the Killeeshil Road, Coolhill Road and Cravenny are at various stages of construction."
Mr Murphy said work on the A5 Western Key Transport Corridor continues to make "significant progress".
Details of the preferred corridor for this scheme were announced last month.
"Roads Service will now be developing a number of route options within the preferred corridor and a series of public consultation events will be held in early 2009 to highlight these options and to invite comments," said the Minister.
Realignment works between Dungannon and Cookstown the A29 Carland Bridge will begin in May 2009, with the procurement process already underway, said Mr Murphy.
"Schemes which have been completed this financial year include the resurfacing in asphalt of 1,800 metres of the A5 Tullyvar Road, resurfacing of the A29 Dungannon Road, Moy and bitmac resurfacing of 1,800 metres of the Whitebridge Road.
"Also completed has been the provision of a right turning lane on the A29 at the Moy Road / Old Moy Road junction in Dungannon and the provision of a pelican crossing at Colebrooke Road, Fivemiletown," he added.
Road Service’s Divisional Roads Manager, Pat Doherty, said: "Other schemes that will be taken forward in the current financial year include the completion of a double right turning lane and footway on the A4 at Killeeshil Crossroads and improvements to the existing footpath in Ardbeg, Dungannon.
The Roads Service report also contained the draft capital programme for 2009-2011.
Schemes including junction improvements on the B43 at the Mullaghmore Road / Tullydraw Road junction and providing footway and cycle links on the Killyman Road in Dungannon.
(PR/JM)
Time and date
CONSTRUCTION DIRECTORY
Construction News
05/12/2008
'Significant Progress' On Dungannon £5.5m Roads Improvement
Latest Construction News
25/11/2024
Northern Ireland-based construction company GRAHAM has been awarded Platinum accreditation by The 5% Club, which is their highest level of accolade. The 5% Club company, a benchmark of investment in future talent, awarded GRAHAM the Platinum membership for their unwavering commitment to empowering ...
25/11/2024
Building and civil engineering contractor Farrans, based in Dunmurry, Northern Ireland, has been selected as one of 19 businesses as preferred partners to SP Energy Networks' record £5.4bn supply chain contract programme. SP Energy Networks have selected the 19 companies to help them deliver the ...
25/11/2024
Energy provider ESB Networks has been working over the weekend to restore power to 60,000 homes predominantly in counties Donegal, Sligo, Mayo and Galway following the impact of Storm Bert. As of 5.10pm, 11,000 of ESB Network's customers remained without power, meaning 49,000 homes had saw their ...
25/11/2024
Alliance has rejected Infrastructure Minister John O'Dowd's claims that NI Water's funding model is 'fit for purpose'. Alliance Infrastructure spokesperson, Andy McMurray, accused the Minister of "burying his head in the sand" over the funding issues and stated that the Minister rejected evidence ...
25/11/2024
Grass Pitch Refurbishment Projects in Sandyford, Dublin, have successfully been completed, Dún Laoghaire-Rathdown County Council (DLR) has announced. Pitches at both Moreen Park and Páirc Uí Bhriain were the subject of upgrade and improvement works as part of an ongoing programme aimed at ...
25/11/2024
Northern Ireland construction company McLaughlin & Harvey placed runner-up for social impact at the Considerate Constructors Scheme (CCS) End of Year Gala. The event, recently held at the Natural History Museum in London, recognises and celebrates outstanding company-wide performance among ...
25/11/2024
Expert water services crews are working to locate and repair a major pipe burst which is impacting water supply across Mid Kerry, Uisce Éireann has announced. The affected raw water pipe provides water to the Mid Kerry Gearha Water Treatment Plant supplying Listry, Beaufort, Killorglin and ...
25/11/2024
Uisce Éireann has temporarily shut down the Dunmanway Water Treatment Plant in Cork after it was impacted due to poor raw water quality from storm flooding. The turbidity of the incoming water for treatment remains high, resulting in the closure of the plant, and reservoirs in the area are now ...
25/11/2024
Irish Government has offered financial support to householders who have been impacted by Storm Bert. The Humanitarian Assistance Scheme provides income-tested financial support to those whose homes have been damaged from flooding and severe weather events and who cannot meet costs for essential ...
25/11/2024
A topographic and hydrographic survey will be carried out from today onwards by Murphy Geospatial Limited for the N17 Knock to Collooney [Atlantic Economic Corridor] Project. The project will consider the upgrade of the existing N17 from Knock in County Mayo to Collooney in County Sligo. The ...