NI Water's contractor, BSG, is scheduled to finish the second of four significant connections on Meadow Lane in Portadown this week.
Following this, the next phase of pipelaying is expected to commence in the Portmore Street area by the end of July.
As part of NI Water's £7.8m Meadow Lane Wastewater Upgrade, the project includes laying over 600 metres of large diameter sewer pipes and building a state-of-the-art wastewater pumping station.
Speaking about the work, NI Water Project Manager, Lisa Hughes said: "We recently completed tunnelling of the 1500mm diameter sewer under Meadow Lane and our contractor, BSG is now working to complete the remaining connections to the existing network.
"Work at the entrance to Portadown Boat Club is due to be completed by Friday 5th July with the next phase of open-cut pipelaying and connection work planned to commence in the vicinity of Portmore Street towards the end of July.
"To facilitate the work safely, Meadow Lane will be closed to southbound traffic at the Portmore Street junction. Access along Meadow Lane from Thomas Street towards Bridge Street will be unaffected. Work is expected to get underway on Monday 29th July and be completed by Friday 6th September. During this time, access to Portmore Street and businesses on Meadow Lane as far as Portmore Street will be via Bridge Street/Meadow Lane.
"While this work is ongoing, access to businesses beyond Portmore Street, including Bannview B&B, McWilliam Car Sales, Portadown Boat Club, the service area of Tesco and the Range as well as the health centre and Baptist Church will be via Thomas Street/Tavanagh Avenue.
"A diversion route for motorists will be signposted and as always our contractor will make every effort to complete the work in the shortest possible timescale. Following the completion of pipelaying at Meadow Lane/Portmore Street junction, some open-cut work on Portmore Street itself will be required. A lane closure will be required on Meadow Lane to facilitate this work and access to Portmore Street will be via Thomas Street during this time. We will provide an update to residents, businesses and the public ahead of this section of work getting underway.
"NI Water and our project team from BSG and McAdam take this opportunity to thank the local community for their continued patience and support during the ongoing £7.8m Meadow Lane Wastewater Upgrade Project."
NI Water's substantial investment aims to meet Northern Ireland Environmental Agency (NIEA) standards by reducing discharges into local watercourses and enabling the closure of five Storm Overflows. Beyond environmental improvements, this infrastructure upgrade will support Portadown's development prospects and economic growth.
Time and date
CONSTRUCTION DIRECTORY
Construction News
04/07/2024
BSG Set To Complete Second Connection On Meadow Lane, Portadown
Latest Construction News
25/11/2024
Northern Ireland-based construction company GRAHAM has been awarded Platinum accreditation by The 5% Club, which is their highest level of accolade. The 5% Club company, a benchmark of investment in future talent, awarded GRAHAM the Platinum membership for their unwavering commitment to empowering ...
25/11/2024
Building and civil engineering contractor Farrans, based in Dunmurry, Northern Ireland, has been selected as one of 19 businesses as preferred partners to SP Energy Networks' record £5.4bn supply chain contract programme. SP Energy Networks have selected the 19 companies to help them deliver the ...
25/11/2024
Energy provider ESB Networks has been working over the weekend to restore power to 60,000 homes predominantly in counties Donegal, Sligo, Mayo and Galway following the impact of Storm Bert. As of 5.10pm, 11,000 of ESB Network's customers remained without power, meaning 49,000 homes had saw their ...
25/11/2024
Alliance has rejected Infrastructure Minister John O'Dowd's claims that NI Water's funding model is 'fit for purpose'. Alliance Infrastructure spokesperson, Andy McMurray, accused the Minister of "burying his head in the sand" over the funding issues and stated that the Minister rejected evidence ...
25/11/2024
Grass Pitch Refurbishment Projects in Sandyford, Dublin, have successfully been completed, Dún Laoghaire-Rathdown County Council (DLR) has announced. Pitches at both Moreen Park and Páirc Uí Bhriain were the subject of upgrade and improvement works as part of an ongoing programme aimed at ...
25/11/2024
Northern Ireland construction company McLaughlin & Harvey placed runner-up for social impact at the Considerate Constructors Scheme (CCS) End of Year Gala. The event, recently held at the Natural History Museum in London, recognises and celebrates outstanding company-wide performance among ...
25/11/2024
Expert water services crews are working to locate and repair a major pipe burst which is impacting water supply across Mid Kerry, Uisce Éireann has announced. The affected raw water pipe provides water to the Mid Kerry Gearha Water Treatment Plant supplying Listry, Beaufort, Killorglin and ...
25/11/2024
Uisce Éireann has temporarily shut down the Dunmanway Water Treatment Plant in Cork after it was impacted due to poor raw water quality from storm flooding. The turbidity of the incoming water for treatment remains high, resulting in the closure of the plant, and reservoirs in the area are now ...
25/11/2024
Irish Government has offered financial support to householders who have been impacted by Storm Bert. The Humanitarian Assistance Scheme provides income-tested financial support to those whose homes have been damaged from flooding and severe weather events and who cannot meet costs for essential ...
25/11/2024
A topographic and hydrographic survey will be carried out from today onwards by Murphy Geospatial Limited for the N17 Knock to Collooney [Atlantic Economic Corridor] Project. The project will consider the upgrade of the existing N17 from Knock in County Mayo to Collooney in County Sligo. The ...