The Parnell Square Project in Dublin city has taken a major leap forwards thanks to a key appointment.
A multi-disciplinary Design Team has been appointed by Dublin City Council to progress the project.
Aecom Ireland, which is leading the team, also serves as Cost Consultant/Project Manager, Structural and Civil Engineer, and Building Services. Other companies involved include Hawkins Brown Architecture (Architect), AWN Consulting (Acoustic Engineer), Jensen Hughes (Fire Safety Engineer) and Chris Mee (PSDS).
The programme for completion of the detailed design works is approximately one year with a commencement date in early 2023. The project will then go to tender, which will take in the order of seven to eight months. Construction of Phase 1 is expected to be completed in 2027.
The appointment of the Design Team along with the on-going demolition and site clearance works, which are nearing completion, mark an important milestone in the delivery of this project.
The scope of design works for the Parnell Square Project Phase 1 includes detailed design of the City library, design review and necessary redesign of the proposed works at the Hugh Lane Gallery and proposed works to the Georgian houses numbers 22, 23, 24, 25, 26, 27 and 28 and complete renovation design to house number 27 Parnell Square North. The design brief also includes tender analysis, construction supervision and handover to client.
Demolition works on the existing Amharclann building, which began last November, are continuing.
Time and date
CONSTRUCTION DIRECTORY
Latest Construction News
25/11/2024
Northern Ireland-based construction company GRAHAM has been awarded Platinum accreditation by The 5% Club, which is their highest level of accolade. The 5% Club company, a benchmark of investment in future talent, awarded GRAHAM the Platinum membership for their unwavering commitment to empowering ...
25/11/2024
Building and civil engineering contractor Farrans, based in Dunmurry, Northern Ireland, has been selected as one of 19 businesses as preferred partners to SP Energy Networks' record £5.4bn supply chain contract programme. SP Energy Networks have selected the 19 companies to help them deliver the ...
25/11/2024
Energy provider ESB Networks has been working over the weekend to restore power to 60,000 homes predominantly in counties Donegal, Sligo, Mayo and Galway following the impact of Storm Bert. As of 5.10pm, 11,000 of ESB Network's customers remained without power, meaning 49,000 homes had saw their ...
25/11/2024
Alliance has rejected Infrastructure Minister John O'Dowd's claims that NI Water's funding model is 'fit for purpose'. Alliance Infrastructure spokesperson, Andy McMurray, accused the Minister of "burying his head in the sand" over the funding issues and stated that the Minister rejected evidence ...
25/11/2024
Grass Pitch Refurbishment Projects in Sandyford, Dublin, have successfully been completed, Dún Laoghaire-Rathdown County Council (DLR) has announced. Pitches at both Moreen Park and Páirc Uí Bhriain were the subject of upgrade and improvement works as part of an ongoing programme aimed at ...
25/11/2024
Northern Ireland construction company McLaughlin & Harvey placed runner-up for social impact at the Considerate Constructors Scheme (CCS) End of Year Gala. The event, recently held at the Natural History Museum in London, recognises and celebrates outstanding company-wide performance among ...
25/11/2024
Expert water services crews are working to locate and repair a major pipe burst which is impacting water supply across Mid Kerry, Uisce Éireann has announced. The affected raw water pipe provides water to the Mid Kerry Gearha Water Treatment Plant supplying Listry, Beaufort, Killorglin and ...
25/11/2024
Uisce Éireann has temporarily shut down the Dunmanway Water Treatment Plant in Cork after it was impacted due to poor raw water quality from storm flooding. The turbidity of the incoming water for treatment remains high, resulting in the closure of the plant, and reservoirs in the area are now ...
25/11/2024
Irish Government has offered financial support to householders who have been impacted by Storm Bert. The Humanitarian Assistance Scheme provides income-tested financial support to those whose homes have been damaged from flooding and severe weather events and who cannot meet costs for essential ...
25/11/2024
A topographic and hydrographic survey will be carried out from today onwards by Murphy Geospatial Limited for the N17 Knock to Collooney [Atlantic Economic Corridor] Project. The project will consider the upgrade of the existing N17 from Knock in County Mayo to Collooney in County Sligo. The ...